Hi there,
we are testing flexmonster atm and I am trying to compare several data in different time slots (as you see in the attached file).
I would like to get the growth for the value "Sum of Bestellmenge" from Date 1 to Date 2.
Can I do this via the UI? If not: how can I do it via code.
Thanks in advance!
Best Regards, Chris

Attachments:
example.png
fields.png

2 answers

Public
Tanya Gryshko Tanya Gryshko Flexmonster July 27, 2018

Hello, Chris,
Thanks for your interest in Flexmonster Pivot!
Such comparison can be done via code only. We suggest checking out this forum thread. Here you will find the instructions and live JSFiddle demo.
Please let me know if you have other questions.
Regards,
Tanya